The St Dubricius project has now been completed. This site will be maintained and updated for the time being. There are always new pieces of information relevant to the project and the church.
The project included the renovation of the decorative design by Sedden and re-roofing the chancel. There was a great deal of documentary research by the team volunteers, and some archaeology. Delays to the project were caused by the discovery of a major structural problem with the roof; bats nesting; and Covid 19. The renovation project was carried out by Sally Strachey Conservation and the archeological work by Herefordshire Archaeology.The Walker organ was also rebuilt
The final part of the project was tidying up the churchyard after the builders had left.